Beginning at 7:00 a.m. on May 8, 2026, JMB Construction (JMB) will be installing the recycled water distribution pipeline on North McDonnell Road, between West Area Drive and West Field Road. Installation will be open cut trench. Flaggers, traffic control, and signage will be on North McDonnell Road during working hours to reduce traffic lanes and vehicle speed through the work zone. Work areas in roadways will be covered with steel plates in non-work hours. There will be increased construction traffic on North McDonnell Road.

Construction Period: May 8, 2026, to June 19, 2026

  • Installation between West Area Drive and North Campus Drive will be performed between the hours of 7:00 a.m. until 5:00 p.m.